The AGP construction Project had a construction duration of 5 months (December 2018 to April 2019), with commissioning successfully completed shortly after.
Survey requirements included pipeline centreline, limits of the construction ROW and any ancillary workspaces surveyed and marked out ahead of ground-disturbing works.